Build Diary

Automatically generated build diary based on work progress, expenses, and issues.

2025-10-03

Sunny, 15°C, wind 5 km/h

On site:

5 (Crew A), 3 (Crew B)

Foundation pour complete. Preparations started for ground-floor walls.

Photo documentation:

Photo 1Photo 2

2025-10-02

Overcast, 12°C, wind 10 km/h

On site:

4 (Crew A)

Continued reinforcing foundation beams. Formwork completed.

2025-10-01

Rainy, 10°C, wind 15 km/h

On site:

5 (Crew A)

Earthworks started for foundations. Topsoil removed. Building axes set out.

Photo documentation:

Photo 1